Gym Construction Update (February 8, 2024)

The construction group is pleased to report our progress for the week ended February 8, 2024.

Site Work:  At this point the site work is all excavated for the entire construction area.  Building footprint, parking lot, cafeteria parking area and various underground drainage for the building.

Concrete:  We have 100% completed the footings, the foundation walls, foundation insulation and backfill of the foundation.

Steel work: This week saw the main building (gymnasium portion) overhead steel going up.  The main “arch” of the building is up and work has commenced on reinforcement of the roof in preparation for roof panels.

We will be reporting weekly on the progress of the project.