Gym Building Update (April 26, 2024)

 Glad to report the work effort at St. Methodios gym project for week ended April 25, 2024. Beatuful spring weather continues to be a blessing and we are making great progress on the frame and exterior finishes of your buildng. Crews from Budel Construction were on site all week....

Gym Building Update (April 19, 2024)

Glad to report the work effort at St. Methodios gym project for week ended April 19, 2024. We have had an excellent week of working even though there have been some scattered showers. Crews from Budel Construction were on site all week.  The stone on the outside of the...

Gym Building Update (April 12, 2024)

Glad to report the work effort at St. Methodios gym project for week ended April 11, 2024. We have had an excellent week of working even though there have been some scattered showers. Crews from Budel Construction were on site all week and the preparatory work is finished for...

Gym Building Update (April 5, 2024)

Glad to report the work effort at St. Methodios gym project for week ended April 5, 2024. Despite the snow and rain of Wednesday and Thursday of this week, good progress was made by all the building structure teams. Crews from Budel Construction were on site to prepare the...

Gym Building Update (March 30, 2024)

The updates of progress this week at the site are exciting to report.  Week ended 3/29/2024 The ceiling on the main gymnasium is complete.  This is put on as a safety measure so when the roof goes on, which starts next week, the workers have additional fall protection.  This...

Gym Building Update (March 22, 2024)

The updates of progress this week at the site are exciting to report.  Week ended 3/21/2024 The ceiling on the main gymnasium is just about complete.  This is put on as a safety measure so when the roof goes on, which starts next week, the workers have additional fall...

Gym Building Update (March 15, 2024)

The construction group is pleased to report our progress for the week ended March 15, 2024. Site Work:  Site work is awaiting another week of good weather before the spring portion of the exterior site work commences again.  In the meantime we are watching the site to dry out...

Gym Building Update (March 8, 2024)

The construction group is pleased to report our progress for the week ended March 8, 2024. Site Work:  At this point the site work is all excavated for the entire construction area.  Building footprint, parking lot, cafeteria parking area and various underground drainage for the building. This week we...

Gym Building Update (March 1, 2024)

The construction group is pleased to report our progress for the week ended March 1, 2024. Site Work:  At this point the site work is all excavated for the entire construction area.  Building footprint, parking lot, cafeteria parking area and various underground drainage for the building. This week we...